The Same Word Means Three Different Things

A PMO could not trust its portfolio reports because one work item name meant a few days on one team and more than a year on another. The fix started with evidence of work already done, not with a debate about definitions.

04 CASCADE
The condition

Three project managers pulled the same epic-level view and got back three different kinds of work.

Three Exports, One Word

A PMO leader in a global IT organization brought us a problem and ruled out the obvious answer before we could offer it. Her project managers could not pull reliable data from the organization's work management tool. Not one of them. And it was not a training problem; she had already checked. They knew how to use the tool. The trouble was that the data inside it meant different things depending on which team you looked at.

She had asked three project managers for the same simple thing: an epic-level view of their project work. She put the three exports side by side. On one team, an epic was two to three days of scope. On another, epics were plainly multi-month commitments. The third export held a couple of epics that had been open for more than a year.

She could not tell whether an epic was a large planning package with substantial scope beneath it, a small and tangible package of work, or something close to granular detail. Every portfolio view her office produced was built on that ambiguity.

Figure 1
One label, three sizes of work
ExportWhat an epic held
First teamTwo to three days of scope
Second teamMulti-month commitments
Third teamSome open more than a year
The same request to three project managers produced three incompatible answers. Any roll-up across them compared things that were not alike.

Nobody Ever Said What an Epic Was

The tool had been in use for years, but it had never been formally implemented. Teams adopted it on their own, learned it as they went, and built their own sense of what each work item was for. Nobody had ever said what an epic is, what a story is, or what either one is meant to hold. Each team settled on a meaning and passed it down internally. In the PMO leader's words, there were now as many definitions as there were teams.

We had seen the pattern before, though rarely at this scale. Groups that develop in isolation build their own vocabulary for the same things. Here, each team's language for work had drifted so far that the same word no longer meant the same thing anywhere in the organization. Portfolio reporting was comparing things that could not be compared.

That is more than a reporting nuisance. The levels of work are the foundation everything above them depends on: consistent reporting, portfolio visibility, capacity planning, and any traceable line from strategy to execution. If an epic can be two days or two years, none of those can be trusted.

Mapping a Landscape Nobody Had Seen

Before designing anything, we needed to see the full extent of the disconnect. We asked for access to the tool and a few days with the technical lead who knew it best. The PMO leader noted that he had been waiting a long time for someone to ask him.

An intern joined for the part of the job that called for patience: methodical documentation of a landscape no one had ever mapped in full. Over several days the technical lead opened every organization and every project in the tool while the intern recorded each work item type in active use, which teams used it, and what was actually inside it.

The finished record documented more than seventy distinct work item types in active use. Many shared a name and carried entirely different meanings. In the epic column alone, one team used the type for two-day tasks and another for work that had been open for two years. The technical lead's read was blunt: this was not a configuration problem. Every team had adopted the tool alone, nobody had coordinated, and the private definitions had compounded over time. The reporting was not broken because the tool was broken. It was broken because the language underneath the tool had never been shared.

Two colleagues comparing printed documents side by side.

Sorting the Work Before Naming It

The usual move is to convene a group and debate definitions. We started with examples instead. The workshop brought together the people who had used the tool longest, the teams whose definitions were furthest apart, and a handful of people who had been openly frustrated by the inconsistency for years.

Before agreeing on what an epic was, the room would look at work the organization had already finished and agree on what it actually had been. Real completed work items came up on screen, pulled from across the organization: projects participants recognized and had worked on. Some had taken two days, some two years. Some had involved one team, some twelve. We asked the room to sort them by what the work actually was, not by what the type field said.

The sorting did not produce an argument about terminology. It produced recognition that the work already fell into distinct layers: strategic multi-year commitments, quarterly business goals, monthly deliverables, bi-weekly functionality, and daily tasks. The layers had always been there. What was missing was agreement on what to call them. By the end of the workshop the organization had five work item types, each with an explicit definition, a working day range, and historical examples mapped to it. Every definition was attached to work the teams had actually done.

We recommended deactivating the old work item types immediately after training. Training sticks only when the environment people return to reflects what they were just taught.

Figure 2
Five layers the work already had
  1. InitiativeStrategic, multi-year commitment
  2. EpicQuarterly business goal
  3. FeatureMonthly deliverable
  4. User storyBi-weekly customer-facing function
  5. TaskDaily, two days or fewer
These levels came out of sorting real completed work, not out of a definitions debate. Each was tied to examples the teams recognized.

The Same View From Every Team

The training took time. When adoption was complete, the PMO's project managers were pulling epic-level views that described the same level of work across every team, every project, and every region. Portfolio reporting that had been comparing incomparable things now rested on one consistent structure.

The fix was not more effort or stricter discipline on the old vocabulary. What had looked like inconsistent people was a language that had never been agreed. Once the words meant one thing, the roll-ups did too.

Figure 3
Work item types, before and after
Work item types in use
More than 70Before
5After
Work item types in use fell from More than 70 (Before) to 5 (After).
The inventory found more than seventy types in active use, many sharing a name with different meanings. The agreed taxonomy defined five, with the old types deactivated after training.

When one word holds two days and two years, the report is not wrong. It is comparing things that were never comparable.

Share With Your Team

Choose who it is for. You send it yourself from your own email; Agileon never writes to your colleagues.

Not sure where to start?

Answer five questions about where work stalls. We send back a starting plan: where to begin and what to look at first.